Level 1 — Basic calculation

Road Earthwork Volumes & Mass-Haul Diagram

Cut and fill volumes between cross-sections by the average end area method, shrinkage and swell, balance and the mass-haul diagram.

How it works — Road Earthwork Volumes & Mass-Haul Diagram

Acut Afill V = (A₁+A₂)/2·L

Inputs

Acut, Afill
Cross-sections

Formula

  • V = (A₁ + A₂)/2·L
  • V_bank = V_fill/(1 − s)
  • M = Σ(V_cut − V_fill,bank)

Results

V
Cut volume (bank)

One station per line: station (m), cut area (m²), fill area (m²).

Reset

Results

Enter your values and press Calculate. The defaults are a worked example.

Formula

V = (A₁ + A₂)/2·L · V_bank = V_fill/(1 − s) · M = Σ(V_cut − V_fill,bank)

Formulas are evaluated in SI units; inputs and results are converted.

Show the math

Worked solution

Press Calculate to see every step with your values substituted.

Calculation level & design standard

Level 1 — Basic calculation

A direct engineering equation.

Preliminary engineering calculation — no jurisdiction-specific code compliance claimed. Verify the applicable requirements with a qualified professional.

Assumptions

  • Average end area method (slightly overestimates for pyramidal shapes).

References

  • AASHTO, A Policy on Geometric Design of Highways and Streets (Green Book), 7th ed. 2018
  • R. L. Peurifoy, Construction Planning, Equipment and Methods

Results are for preliminary design and education. Verify against the governing code and have critical work checked by a licensed professional engineer.