Level 2 — Engineering approximation

Building Electrical Load & Transformer Size

Connected and demand load, power factor, current, diversity and the next standard transformer size from a load schedule with your own demand factors.

How it works — Building Electrical Load & Transformer Size

Σ P·DF S, I

Inputs

P·DF
Load schedule

Formula

  • P_d = Σ P_i·DF_i
  • S_d = √(P_d² + Q_d²)
  • I = S/(√3·V)
  • S_design = S_d(1 + growth)

Results

Σ P·DF
Demand load
S, I
Demand current

One load per line: name, connected kW, demand factor (0–1) and power factor (optional, default 0.9).

Reset

Results

Enter your values and press Calculate. The defaults are a worked example.

Formula

P_d = Σ P_i·DF_i · S_d = √(P_d² + Q_d²) · I = S/(√3·V) · S_design = S_d(1 + growth)

The default schedule is the industrial-facility example: two motors, lighting, HVAC and EV charging. Change the EV line and every result updates.

Show the math

Worked solution

Press Calculate to see every step with your values substituted.

Calculation level & design standard

Level 2 — Engineering approximation

A preliminary engineering model with the simplifications listed under Assumptions.

Preliminary engineering calculation — no jurisdiction-specific code compliance claimed. Verify the applicable requirements with a qualified professional.

Assumptions

  • Demand factors and power factors are the values you enter; no code demand factors are built in.
  • Loads are balanced across the phases.

References

  • IEEE Std 141 (Red Book): Electric Power Distribution for Industrial Plants
  • IEEE Std 241 (Gray Book): Commercial building power systems
  • IEC 60364-3: Assessment of general characteristics

Results are for preliminary design and education. Verify against the governing code and have critical work checked by a licensed professional engineer.