Level 4 — Numerical analysis

Load Flow (Newton–Raphson Power Flow)

Bus voltages and angles, generator outputs, line flows and losses of an N-bus network solved by the Newton–Raphson method, with a one-line view.

How it works — Load Flow (Newton–Raphson Power Flow)

1 3 2 P, Q |V|∠δ

Inputs

P, Q, |V|
Bus data
R, X
Line data

Formula

  • P_i − jQ_i = V_i*·Σ Y_ik V_k
  • [ΔP; ΔQ] = J·[Δδ; Δ|V|] (Newton–Raphson, polar form)

Results

|V|∠δ
Lowest bus voltage
P, Q
Slack bus generation P
Ploss
Total losses P

One bus per line: name, type (slack, pv or pq), voltage set-point (pu, slack and PV), generation P (MW), load P (MW), load Q (Mvar).

One line per row: from bus, to bus, series R and X (pu on the system base) and optional total line charging B (pu).

Reset

Results

Enter your values and press Calculate. The defaults are a worked example.

Formula

P_i − jQ_i = V_i*·Σ Y_ik V_k · [ΔP; ΔQ] = J·[Δδ; Δ|V|] (Newton–Raphson, polar form)

Formulas are evaluated in SI units; inputs and results are converted.

The default network reproduces Saadat's three-bus Newton–Raphson example (Power System Analysis, Example 6.11).

One-line diagram

Buses with their solved voltage (pu) and angle; line labels show the real power flow in MW and its direction.

Show the math

Worked solution

Press Calculate to see every step with your values substituted.

Calculation level & design standard

Level 4 — Numerical analysis

A numerical solver: matrix analysis, iteration or time integration.

Preliminary engineering calculation — no jurisdiction-specific code compliance claimed. Verify the applicable requirements with a qualified professional.

Assumptions

  • Balanced, positive-sequence steady state; π-model lines on a common MVA base.
  • Generator reactive-power limits, transformer taps and shunt devices are not modelled.
  • Convergence tolerance 10⁻⁸ pu on the power mismatches.

References

  • H. Saadat, Power System Analysis
  • W. F. Tinney, C. E. Hart (1967), Power flow solution by Newton's method, IEEE Trans. PAS

Results are for preliminary design and education. Verify against the governing code and have critical work checked by a licensed professional engineer.