Level 1 — Basic calculation

Per-Unit System & Change of Base

Base impedance and current of a three-phase system, conversion of ohms to per unit and of a per-unit impedance to a new MVA and kV base.

How it works — Per-Unit System & Change of Base

Sbase Vbase Zbase = V²/S Zpu = Z / Zbase

Inputs

Sbase
Base power (three-phase) (MVA)
Vbase
Base voltage (line-to-line) (kV)
Z
Impedance to convert (ohms) (Ω)

Formula

  • Z_base = kV²/MVA
  • I_base = MVA/(√3·kV)
  • Z_pu = Z/Z_base
  • Z_new = Z_old(kV_old/kV_new)²(MVA_new/MVA_old)

Results

Zbase
Base impedance Z_base
Ibase
Base current I_base
Convert ohms → per unit
Change of base
Reset

Results

Enter your values and press Calculate. The defaults are a worked example.

Formula

Z_base = kV²/MVA · I_base = MVA/(√3·kV) · Z_pu = Z/Z_base · Z_new = Z_old(kV_old/kV_new)²(MVA_new/MVA_old)

Formulas are evaluated in SI units; inputs and results are converted.

Show the math

Worked solution

Press Calculate to see every step with your values substituted.

Calculation level & design standard

Level 1 — Basic calculation

A direct engineering equation.

Preliminary engineering calculation — no jurisdiction-specific code compliance claimed. Verify the applicable requirements with a qualified professional.

Assumptions

  • Three-phase base: MVA is the three-phase power and kV the line-to-line voltage.

References

  • J. D. Glover, M. S. Sarma, T. Overbye, Power System Analysis and Design
  • IEEE Std 399 (Brown Book): Power systems analysis

Results are for preliminary design and education. Verify against the governing code and have critical work checked by a licensed professional engineer.