Pump Head, Power & NPSH

Total dynamic head, shaft and motor power, NPSH available and the system curve for a pumping line.

How it works — Pump Head, Power & NPSH

Q Δz zs η hf

Inputs

Q
Flow rate (gpm)
Δz
Static lift z₂ − z₁ (ft)
zs
Suction static head z_s (ft)
η
Pump efficiency (%)

Formula

  • H = Δz + Δp/ρg + h_f + h_m
  • P = ρgQH / η
  • NPSHa = (p_atm − p_v)/ρg + z_s − h_f,s

Results

H
Total dynamic head
hf
Friction head loss
P
Pump shaft power
NPSHa
NPSH available
Flow and pipe
Elevations and pressures

Positive if the discharge tank is pressurised

Fluid
Pump and motor
Suction side (NPSH)

Atmospheric at sea level ≈ 101.3 kPa

Positive if the liquid level is above the pump centreline

Reset

Results

Enter your values and press Calculate. The defaults are a worked example.

Formula

H = Δz + Δp/ρg + (fL/D + ΣK)·v²/2g · P = ρgQH/η · NPSHa = (p_atm − p_v)/ρg + z_s − h_f,s

Formulas are evaluated in SI units; inputs and results are converted.

NPSH is flagged when the margin is below 10 % or 0.5 m. Choose a pump whose curve crosses the system curve at the duty point.

Show the math

Worked solution

Press Calculate to see every step with your values substituted.

Assumptions

  • Steady, incompressible, fully developed flow.
  • Full circular pipe of constant inside diameter.
  • Turbulent friction factor from the Swamee–Jain approximation of Colebrook (within ±1 % for 5000 ≤ Re ≤ 10⁸); laminar f = 64/Re.
  • Suction line has the same diameter as the discharge line and an entrance loss K = 0.5.
  • Water properties from temperature correlations (density ±0.01 %, viscosity ±2 %, vapour pressure ±1 %).
  • Velocity head at the outlet is included in ΣK (exit loss K = 1).

References

  • I. J. Karassik et al., Pump Handbook
  • ANSI/HI 9.6.1 — Rotodynamic pumps: guideline for NPSH margin
  • Crane Co., Technical Paper No. 410: Flow of Fluids Through Valves, Fittings and Pipe
  • IAPWS formulations for the properties of water (fitted correlations)

Results are for preliminary design and education. Verify against the governing code and have critical work checked by a licensed professional engineer.

Sign in

or with email

Forgot password?