Level 2 — Engineering approximation

Standby Generator Sizing (Running Load & Motor Starting)

Preliminary standby generator rating from the running load and the largest motor started last, checking the transient voltage dip with the generator's subtransient reactance.

How it works — Standby Generator Sizing (Running Load & Motor Starting)

G M Sstart Xd″, ΔV

Inputs

Sstart
Largest motor (started last) (kW)
Xd″
Generator subtransient reactance X″d (%)
ΔV
Allowed voltage dip (%)

Formula

  • S_run = P/PF
  • S_start = P_m·(LRkVA/kW)·k
  • ΔV ≈ X″d/(X″d + S_gen/S_start)
  • P_gen = S_gen·PF_gen

Results

G
Recommended standby generator rating

NEMA code G ≈ 6–7 kVA/hp ≈ 8–9 kVA/kW

Reset

Results

Enter your values and press Calculate. The defaults are a worked example.

Formula

S_run = P/PF · S_start = P_m·(LRkVA/kW)·k · ΔV ≈ X″d/(X″d + S_gen/S_start) · P_gen = S_gen·PF_gen

Formulas are evaluated in SI units; inputs and results are converted.

Show the math

Worked solution

Press Calculate to see every step with your values substituted.

Calculation level & design standard

Level 2 — Engineering approximation

A preliminary engineering model with the simplifications listed under Assumptions.

Preliminary engineering calculation — no jurisdiction-specific code compliance claimed. Verify the applicable requirements with a qualified professional.

Assumptions

  • The largest motor starts last with all other loads running; one load step.
  • Voltage dip from the subtransient reactance only (AVR response ignored).

References

  • IEEE Std 446 (Orange Book): Emergency and standby power systems
  • NEMA MG 1: Motors and generators

Results are for preliminary design and education. Verify against the governing code and have critical work checked by a licensed professional engineer.